Our final grade beam pour was this past week.  The utility contractor passed their water test and are in the process of raising the fire hydrants.  The plumbing and electrical contractors finished their underslab utilities.  Planks will be ready to start pouring next week.  Final grading of the site paving areas is underway and we'll begin paving later this month.

 South grade beams poured.  North side being formed.

 Final grade beam pour

 UFER clamp installed

 Underslab floor drains installed

 Gas line being installed

SW manhole was demoed and getting ready to repour