Monday, May 19, 2014

May 15, 2014

We have had a few rain days, but the pictures below show the progress we are making on the fire lane and associated paving for the parking.  Once the fire lane is complete we will be able to start framing.


 Thickened concrete for dumpster pad

 Roof drain system



Friday, May 2, 2014

May 1, 2014

The building pad has been poured and the lime stabilization for the fire lane is complete.  We have gas, water, and electricity to the building.  Our concrete guys started working on forming up the site paving on the south side of the project.  Paving will take a few weeks and then we'll be ready to start framing.












Thursday, May 1, 2014

April 17, 2014

Our underslab utilities are in and we were able to pour the building slab.  We started working on the fire lane which we need to complete before we start framing.