Friday, May 2, 2014

May 1, 2014

The building pad has been poured and the lime stabilization for the fire lane is complete.  We have gas, water, and electricity to the building.  Our concrete guys started working on forming up the site paving on the south side of the project.  Paving will take a few weeks and then we'll be ready to start framing.